DISCLAIMER - NIKZAFRI.BLOGSPOT.COM

Today, Knowledge Management today are not limited merely to : (A) 'knowing' or 'reading lots of books/scholarly articles' or (B) data mining, analysis, decision making, preventive actions, or (C) some Human Resources Management issue or (D) some ICT issue. Knowledge Management is about putting your knowledge, skills and competency into practice and most important IT WORKS! For you and your company or your business (Nik Zafri) Offering the best training and consultancy.

The information comprised in this section is not, nor is it held out to be, a solicitation of any person to take any form of investment decision. The content of the nikzafri.blogspot.com does not constitute advice or a recommendation by nikzafri.blogspot.com and should not be relied upon in making (or refraining from making) any decision relating to investments or any other matter. You should consult your own independent financial adviser and obtain professional advice before exercising any investment decisions or choices based on information featured in this nikzafri.blogspot.com can not be held liable or responsible in any way for any opinions, suggestions, recommendations or comments made by any of the contributors to the various columns on nikzafri.blogspot.com nor do opinions of contributors necessarily reflect those of http://www. nikzafri.blogspot.com

In no event shall nikzafri.blogspot.com be liable for any damages whatsoever, including, without limitation, direct, special, indirect, consequential, or incidental damages, or damages for lost profits, loss of revenue, or loss of use, arising out of or related to the nikzafri.blogspot.com or the information contained in it, whether such damages arise in contract, negligence, tort, under statute, in equity, at law or otherwise.


MY EMPLOYERS AND CLIENTELLES




A THOUGHT

It’s wonderful to revisit the past, though not every memory is nostalgic some can drain your spirit to live. I find the present while learning valuable lessons from the past (so they’re not repeated), and focus on the future gives me a sense of closure, ownership, even drives me to move forward, and feels truly empowering.

Perhaps it's time to recite this daily mantra - that "enough is enough" - "no more being a victim, I'm retaking control of myself and my life"

BIODATA - NIK ZAFRI



 



NIK ZAFRI BIN ABDUL MAJID,
CONSULTANT/TRAINER
Email: nikzafri@yahoo.com, nikzafri@gmail.com
https://nikzafri.wixstudio.com/nikzafriv2

Kelantanese, Alumni of Sultan Ismail College Kelantan (SICA), Business Management/Administration, IT Competency Cert, Certified Written English Professional US. Has participated in many seminars/conferences (local/ international) in the capacity of trainer/lecturer and participant.

Affiliations :- Council/Network Member of Gerson Lehrman Group, Institute of Quality Malaysia, Auditor ISO 9000 IRCAUK, Auditor OHSMS (SIRIM and STS) /EMS ISO 14000 and Construction Quality Assessment System CONQUAS, CIDB (Now BCA) Singapore),

* Possesses almost 30 years of experience/hands-on in the multi-modern management & technical disciplines (systems & methodologies) such as Knowledge Management (Hi-Impact Management/ICT Solutions), Quality (TQM/ISO), Safety Health Environment, Civil & Building (Construction), Manufacturing, Motivation & Team Building, HR, Marketing/Branding, Business Process Reengineering, Economy/Stock Market, Contracts/Project Management, Finance & Banking, etc. He was employed to international bluechips involving in national/international megaprojects such as Balfour Beatty Construction/Knight Piesold & Partners UK, MMI Insurance Group Australia, Hazama Corporation (Hazamagumi) Japan (with Mitsubishi Corporation, JA Jones US, MMCE and Ho-Hup) and Sunway Construction Berhad (The Sunway Group of Companies). Among major projects undertaken : Pergau Hydro Electric Project, KLCC Petronas Twin Towers, LRT Tunnelling, KLIA, Petronas Refineries Melaka, Putrajaya Government Complex, Sistem Lingkaran Lebuhraya Kajang (SILK), Mex Highway, KLIA1, KLIA2 etc. Once serviced SMPD Management Consultants as Associate Consultant cum Lecturer for Diploma in Management, Institute of Supervisory Management UK/SMPD JV. Currently – Associate/Visiting Consultants/Facilitators, Advisors/Technical Experts for leading consulting firms (local and international), certification bodies including project management. To name a few – Noma SWO Consult, Amiosh Resources, Timur West Consultant Sdn. Bhd., TIJ Consultants Group (Malaysia and Singapore), QHSEL Consultancy Sdn. Bhd.

He is also currently holding the Position of Principal Consultant/Executive Director (Special Projects) - Systems and Methods, ESG, QHSE at QHSEL Consultancy Sdn. Bhd.* Ex-Resident Weekly Columnist of Utusan Malaysia (1995-1998) and have produced more than 100 articles related to ISO-9000– Management System and Documentation Models, TQM Strategic Management, Occupational Safety and Health (now OHSAS 18000) and Environmental Management Systems ISO 14000. His write-ups/experience has assisted many students/researchers alike in module developments based on competency or academics and completion of many theses. Once commended by the then Chief Secretary to the Government of Malaysia for his diligence in promoting and training the civil services (government sector) based on “Total Quality Management and Quality Management System ISO-9000 in Malaysian Civil Service – Paradigm Shift Scalar for Assessment System”

Among Nik Zafri’s clients : Adabi Consumer Industries Sdn. Bhd, (MRP II, Accounts/Credit Control) The HQ of Royal Customs and Excise Malaysia (ISO 9000), Veterinary Services Dept. Negeri Sembilan (ISO 9000), The Institution of Engineers Malaysia (Aspects of Project Management – KLCC construction), Corporate HQ of RHB (Peter Drucker's MBO/KRA), NEC Semiconductor - Klang Selangor (Productivity Management), Prime Minister’s Department Malaysia (ISO 9000), State Secretarial Office Negeri Sembilan (ISO 9000), Hidrological Department KL (ISO 9000), Asahi Kluang Johor(System Audit, Management/Supervisory Development), Tunku Mahmood (2) Primary School Kluang Johor (ISO 9000), Consortium PANZANA (HSSE 3rd Party Audit), Lecturer for Information Technology Training Centre (ITTC) – Authorised Training Center (ATC) – University of Technology Malaysia (UTM) Kluang Branch Johor, Kluang General Hospital Johor (Management/Supervision Development, Office Technology/Administration, ISO 9000 & Construction Management), Kahang Timur Secondary School Johor (ISO 9000), Sultan Abdul Jalil Secondary School Kluang Johor (Islamic Motivation and Team Building), Guocera Tiles Industries Kluang Johor (EMS ISO 14000), MNE Construction (M) Sdn. Bhd. Kota Tinggi Johor (ISO 9000 – Construction), UITM Shah Alam Selangor (Knowledge Management/Knowledge Based Economy /TQM), Telesystem Electronics/Digico Cable(ODM/OEM for Astro – ISO 9000), Sungai Long Industries Sdn. Bhd. (Bina Puri Group) - ISO 9000 Construction), Secura Security Printing Sdn. Bhd,(ISO 9000 – Security Printing) ROTOL AMS Bumi Sdn. Bhd & ROTOL Architectural Services Sdn. Bhd. (ROTOL Group) – ISO 9000 –Architecture, Bond M & E (KL) Sdn. Bhd. (ISO 9000 – Construction/M & E), Skyline Telco (M) Sdn. Bhd. (Knowledge Management),Technochase Sdn. Bhd JB (ISO 9000 – Construction), Institut Kefahaman Islam Malaysia (IKIM – ISO 9000 & Internal Audit Refresher), Shinryo/Steamline Consortium (Petronas/OGP Power Co-Generation Plant Melaka – Construction Management and Safety, Health, Environment), Hospital Universiti Kebangsaan Malaysia (Negotiation Skills), Association for Retired Intelligence Operatives of Malaysia (Cyber Security – Arpa/NSFUsenet, Cobit, Till, ISO/IEC ISMS 27000 for Law/Enforcement/Military), T.Yamaichi Corp. (M) Sdn. Bhd. (EMS ISO 14000) LSB Manufacturing Solutions Sdn. Bhd., (Lean Scoreboard (including a full development of System-Software-Application - MSC Malaysia & Six Sigma) PJZ Marine Services Sdn. Bhd., (Safety Management Systems and Internal Audit based on International Marine Organization Standards) UNITAR/UNTEC (Degree in Accountacy – Career Path/Roadmap) Cobrain Holdings Sdn. Bhd.(Managing Construction Safety & Health), Speaker for International Finance & Management Strategy (Closed Conference), Pembinaan Jaya Zira Sdn. Bhd. (ISO 9001:2008-Internal Audit for Construction Industry & Overview of version 2015), Straits Consulting Engineers Sdn. Bhd. (Full Integrated Management System – ISO 9000, OHSAS 18000 (ISO 45000) and EMS ISO 14000 for Civil/Structural/Geotechnical Consulting), Malaysia Management & Science University (MSU – (Managing Business in an Organization), Innoseven Sdn. Bhd. (KVMRT Line 1 MSPR8 – Awareness and Internal Audit (Construction), ISO 9001:2008 and 2015 overview for the Construction Industry), Kemakmuran Sdn. Bhd. (KVMRT Line 1 - Signages/Wayfinding - Project Quality Plan and Construction Method Statement ), Lembaga Tabung Haji - Flood ERP, WNA Consultants - DID/JPS -Flood Risk Assessment and Management Plan - Prelim, Conceptual Design, Interim and Final Report etc., Tunnel Fire Safety - Fire Risk Assessment Report - Design Fire Scenario), Safety, Health and Environmental Management Plans leading construction/property companies/corporations in Malaysia, Timur West Consultant : Business Methodology and System, Information Security Management Systems (ISMS) ISO/IEC 27001:2013 for Majlis Bandaraya Petaling Jaya ISMS/Audit/Risk/ITP Technical Team, MPDT Capital Berhad - ISO 9001: 2015 - Consultancy, Construction, Project Rehabilitation, Desalination (first one in Malaysia to receive certification on trades such as Reverse Osmosis Seawater Desalination and Project Recovery/Rehabilitation), ABAC Centre of Excellence UK (ABMS ISO 37001) Joint Assessment (Technical Expert)

He is also rediscovering long time passions in Artificial Intelligence, ICT and National Security, Urban Intelligence/Smart Cities, Environmental Social and Governance, Solar Energy, Data Centers - BESS, Tiers etc. and how these are being applied.

* Has appeared for 10 consecutive series in “Good Morning Malaysia RTM TV1’ Corporate Talk Segment discussing on ISO 9000/14000 in various industries. For ICT, his inputs garnered from his expertise have successfully led to development of work-process e-enabling systems in the environments of intranet, portal and interactive web design especially for the construction and manufacturing. Some of the end products have won various competitions of innovativeness, quality, continual-improvements and construction industry award at national level. He has also in advisory capacity – involved in development and moderation of websites, portals and e-profiles for mainly corporate and private sectors, public figures etc. He is also one of the recipients for MOSTE Innovation for RFID use in Electronic Toll Collection in Malaysia.

Note :


TO SEE ALL ARTICLES

ON THE"LABEL" SECTION BELOW (RIGHT SIDE COLUMN), YOU CAN CLICK ON ANY TAG - TO READ ALL ARTICLES ACCORDING TO ITS CATEGORY (E.G. LABEL : CONSTRUCTION) OR GO TO THE VERY END OF THIS BLOG AND CLICK "Older Posts"

Tuesday, February 10, 2026

NCR : Highway Construction : Box Girder Alignment Deviation

 


This case study is from 2012. All project details have been intentionally anonymised to protect confidentiality. I am grateful to the former Superintending Consultant for sharing this valuable reference.

NCR No.: NCR-HWY-...-.... | Date Raised: 202x-0X-xx

Area: Bridge Superstructure : Box Girder Segment B2,

Chainage CH 12+300 to CH 12+320, Gridline C1–C2

Clause Reference: JKR Bridge Works Clause 7.3.2

Severity: Medium | Disposition: Rework (Realignment)

1.0 PROJECT CONTEXT

Highway bridge works involving cast-in-situ reinforced concrete Box Girders.

During routine inspection of the box girder segment placement prior to post-tensioning, an alignment deviation was detected.

2.0 DESCRIPTION OF THE NON-CONFORMANCE

The horizontal alignment of Box Girder Segment B2 deviated +45 mm from approved design centreline after formwork stripping.

2.1 Tolerance Reference

  • JKR Specification: Civil Works Clause 7.3.2 – Alignment tolerance for bridge superstructure: ±30 mm,

  • BS 5400 / Eurocode / AASHTO: Similar ±25-40 mm depending on span and structure class.

  • JKR QA/QC Plan (Project Specific): Alignment control and surveying tolerances.

This deviation exceeds the allowable tolerance (±30 mm)

2.2 Evidence/Attachments

  • Site photographs,

  • Survey records,

  • Inspection checklist,

  • Test results

  • Sketch/marked-up drawing

Classification : Medium Risk NCR (not severe to halt works but must be corrected before post-tensioning).

3.0 FINDINGS


4.0 REFERENCE

  • JKR Specification for Bridge Works,

  • JKR Standard Drawings (SJ / SK / SP series),

  • BS 5400 / Eurocode 2 / AASHTO LRFD (for reference),

  • Project QA/QC Plan & Inspection Test Plan (ITP)

  • Survey Control Method Statement

5.0 CALCULATIONS/SURVEY VALIDATION

Survey Data (Before & After)

  • Design Line: X = 1,250.000 m

  • Measured After Stripping: X = 1,250.045 m

  • Deviation: Δ = 0.045 m ⇒ 45 mm

5.1 Tolerance Check

| 0.045m | =45mm>30mm (JKR tolerance)

= OUT OF TOLERANCE

5.2 Effect on Post-Tensioning

Misalignment may induce eccentricities, resulting in:

  • Stress redistribution

  • Potential cracking

  • Post-tensioning stressing inefficiencies

A quick simplified check:


6.0 METHOD FOR CORRECTIVE ACTION (Corrective Realignment of Box Girder Segment B2)

6.1 Activities

Set up precision total station and re-establish control points.

  • Verify existing alignment and mark deviation.

  • Loosen temporary supports (if any) under segment B2.

  • Apply controlled jacking (using hydraulic jacks) to shift girder laterally to design centreline.

  • Monitor moves in real time (surveyor continuously records).

  • Lock off and resecure formwork anchors and supports.

  • Re-survey final position and record in NCR corrective action.

  • Pre-stress only after verification by QA/QC and Resident Engineer.

6.2 Resources

  • Hydraulic jacks and load cells

  • Total station and Optical targets

  • Trained survey crew

  • Supervision by Structural Engineer

6.2 Acceptance Criteria

  • Final alignment within ±20 mm (stricter than JKR tolerance for safety)

  • Record updated survey logs

7.0 ROOT CAUSE ANALYSIS


oot Causes

  • Survey control points not adequately protected during casting = drifted,

  • Inadequate formwork bracing = lateral movement under concrete pressure.

8.0 CORRECTIVE ACTIONS

Immediate:

  • Realign girder segment (as per method statement),

  • Reestablish and secure all survey control points,

  • Resurvey all adjacent segments.

9.0 ROLES, RESPONSIBILITIES AND AUTHORITIES


10.0 PREVENTIVE ACTIONS

  • Update Survey Control Method Statement,,

  • Install redundant benchmark targets,,

  • Daily verification of bracing and formwork stability,

  • Pre-pour check sign-off with 2-person independent verification,

  • Toolbox talk for crew on tolerance requirements

11.0 IMPACT ASSESSMENT AND RISK REGISTER UPDATE