Friday, April 03, 2026

Sample (Method Statement) : Installation of Structural Steel and Piping System

Disclaimer: The format of the document should be aligned with the specific contract requirements and the nature of the project. The content provided here highlights key considerations when developing a method statement. Two basic framework formats are included for reference:

  • Industrial, oil & gas, power plant, or heavy engineering projects

  • EPC, industrial plant, or infrastructure projects

Please note that these formats should be further customized to suit project needs. Additional elements may be incorporated where applicable, such as a detailed Inspection and Test Plan (ITP) matrix commonly used in oil & gas projects, welding inspection flow, construction workflow diagrams, and quality assurance (QA) forms typically required by consultants.

1.1 SCOPE OF WORK

This method statement covers the fabrication, installation, alignment, welding, inspection, and testing of structural steel members and piping systems including pipes, fittings, and flanges made from carbon steel and stainless steel used in industrial or infrastructure facilities.

1.2 REFERENCES

Works shall comply with recognized international standards including:

  • ASTM A36 : Structural carbon steel

  • ASTM A106 Grade B : Carbon steel seamless pipes

  • ASTM A312 : Stainless steel pipes

  • ASME B16.5 : Pipe flanges and flanged fittings

  • ASME B16.9 : Butt-welding fittings

  • ASME Section IX : Welding qualifications

1.4 PROCEDURE

1.4.1 Material Inspection

  • Verify material certificates (MTC) and heat numbers.

  • Confirm compliance with project specifications.

  • Inspect for damage, corrosion, or deformation.

1.4.2 Structural Steel Installation

  • Structural members are fabricated off-site or on-site as per approved shop drawings.

  • Surface preparation and protective coating / galvanizing are applied if required.

  • Members are lifted using cranes and installed according to grid alignment and elevation.

  • Connections are completed using high strength bolts or welding.

  • Final plumbness, level, and alignment checks are carried out.

1.4.3 Pipe Installation

  • Pipes are cut, beveled, and aligned before welding.

  • Pipe supports are installed according to piping drawings.

  • Pipes are installed progressively along the pipe rack or equipment connections.

  • Fittings and flanges are installed to facilitate direction change and equipment interface.

1.4.4 Welding

  • Welding is carried out following approved WPS and PQR.

  • Welders must be certified under relevant codes.

  • Preheating and post weld heat treatment (PWHT) are applied where required.

1.4.5 Inspection and Testing/QA-QC

Quality control includes:

  • Visual inspection of welds

  • Non-destructive testing (RT/UT/PT/MT)

  • Dimensional verification

  • Hydrostatic pressure testing of piping system

Inspection hold points should be identified where client or consultant approval is required before proceeding to the next stage (Systems must pass inspection prior to commissioning)

2. MATERIAL SELECTION (Justifications)

Material selection for structural and piping systems is based on strength, corrosion resistance, service conditions, cost efficiency, and maintenance requirements.

2.1 Carbon Steel (Structural Steel and Utility Piping)

Carbon steel is commonly used for:

  • Structural frames

  • Pipe racks

  • Utility pipelines (water, steam, air)

Advantages

  • High mechanical strength

  • Cost-effective and widely available

  • Good weldability

  • Suitable for non-corrosive environments

Typical Applications

  • Cooling water systems

  • Firewater pipelines

  • Compressed air systems

  • Structural support members

2.2 Stainless Steel (Process Piping)

Stainless steel is selected for services involving:

  • Corrosive chemicals

  • High purity processes

  • Hygienic or contamination-sensitive systems

Advantages

  • Excellent corrosion resistance

  • High durability and longer service life

  • Resistant to oxidation and chemical attack

  • Suitable for high temperature environments

Typical Applications

  • Chemical processing lines

  • Pharmaceutical or food-grade piping

  • Acid or solvent transport systems

  • Offshore or marine environments

2.3 Combined Material Strategy

Using carbon steel for structural support and utility lines while installing stainless steel for corrosive or critical process lines provides:

  • Optimized cost efficiency

  • Improved reliability and safety

  • Reduced maintenance requirements

  • Longer operational lifespan of the facility

This hybrid material strategy is commonly applied in industrial plants, refineries, power plants, and water treatment facilities.

3. RISK ASSESSMENT (HSE)

(Industrial, oil & gas, power plant, or heavy engineering projects)

3.1 Scope

Coverage of Hazards :

  • Structural steel erection

  • Carbon steel & stainless steel piping installation

  • Welding, grinding, lifting, hydrotesting

3.2 Hazard Identification & Control Measures

A. Lifting & Erection of Structural Steel

Hazards

  • Falling objects

  • Crane failure

  • Working at height

Control Measures

  • Approved lifting plan & load calculation

  • Certified crane & lifting gears inspection

  • Competent rigger & signalman

  • Full body harness for work > 2m

  • Barricaded exclusion zones

B. Welding & Cutting Works

Hazards

  • Fire & explosion

  • Arc flash & burns

  • Fumes inhalation

Control Measures

  • Hot Work Permit system

  • Fire watch & extinguishers

  • Welding screens

  • Proper ventilation

  • PPE: welding helmet, gloves, FR clothing

Welding qualification in accordance with ASME Section IX.

C. Piping Installation & Hydrotest

Hazards

  • Line burst during hydrotest

  • Stored energy release

  • Slips/trips

Control Measures

  • Calibrated pressure gauges

  • Test barricade & warning signage

  • Gradual pressurization

  • Pressure relief valve installed

  • Controlled access during testing

D. Handling Stainless Steel

Hazards

  • Cross-contamination from carbon steel tools

  • Sharp edges

Control Measures

  • Dedicated SS tools & brushes

  • Segregated storage area

  • Edge protection gloves

4. INSPECTION AND TEST PLAN (ITP)


5. QUALITY ASSURANCE

5.1 Pre-Construction

  • Approved IFC drawings

  • Approved WPS / PQR

  • Welder qualification records

  • Material approval from client

5.2 During Construction

  • Heat number traceability maintained

  • Fit-up inspection prior to welding

  • Bolt tightening sequence followed

  • Proper segregation of CS and SS materials

  • Surface protection applied

5.3 Post-Construction

  • NDT completed and accepted

  • Hydrotest completed

  • Punch list closed

  • As-built drawings updated

  • Final QA dossier compiled (included in the Project Quality Plan or Project Execution Plan (depending on role in the project whether a contractor/sub-contractor/consultant)

6. MATERIAL TRACEABILITY

6.1 Objective

To ensure full traceability of structural steel, pipes, fittings, and flanges from delivery to final installation.

6.2 Procedure

A. RECEIVING (INCOMING) INSPECTION

  • Verify Mill Test Certificates (MTC)

  • Check heat number stamped on materials

  • Assign internal tracking number

B. STORAGE AND SEGREGATION

  • Separate carbon steel and stainless steel materials

  • Store stainless steel away from contamination

  • Tag materials with identification code

C. FABRICATION/INSTALLATION

  • Heat number transferred to cut pieces

  • Weld map prepared for piping system

  • Welding recorded in weld log

D. DOCUMENTATION

Maintain:

  • Material Receiving Report (MRR)

  • Weld Traceability Log

  • NDT Reports

  • Hydrotest Reports

  • Final Material Dossier

7. ENGINEERING RATIONALE

The integration of:

  • Carbon steel for structural and non-corrosive utility service

  • Stainless steel for corrosive or critical process service

ensures:

  • Structural integrity

  • Operational reliability

  • Cost optimization

  • Regulatory compliance

  • Long-term asset durability


(EPC, industrial plant, or infrastructure projects)

1. RISK ASSESSMENT (HSE)

Risk assessments must comply with occupational safety requirements such as ISO 45001 and project safety procedures.



Mandatory Personal Protective Equipment (PPE)

  • Safety helmet

  • Safety shoes

  • Welding shield

  • Fire resistant gloves

  • Safety goggles

  • Full body harness for work at height

Emergency procedures must include first aid availability, fire extinguishers, and evacuation plan.

2. INSPECTION AND TEST PLAN

Inspection activities follow engineering standards including ASME B31.3 for piping systems.


Inspection hold points should be identified where client or consultant approval is required before proceeding to the next stage (Systems must pass inspection prior to commissioning)

3. QUALITY ASSURANCE

A quality checklist ensures compliance with project specifications.

Pre-Installation

  • Approved shop drawings available

  • Material certificates verified

  • Welding procedure approved

  • Welder qualification valid

  • Inspection tools calibrated

During Installation

  • Pipe alignment verified

  • Correct fittings and flanges installed

  • Welding parameters monitored

  • Bolt tightening sequence followed

  • Structural members properly aligned

Post Installation

  • NDT inspection completed

  • Pressure testing completed

  • Surface coating / painting completed

  • Final inspection signed by QA/QC team

4. MATERIAL TRACEABILITY

Material traceability ensures that every component installed can be traced back to its origin.

Each material must have:

  • Material Test Certificate (MTC)

  • Heat number identification

  • Manufacturer details

  • Batch or lot number

Common traceability practices include:

  • Stamping or tagging heat numbers on pipes

  • Marking structural steel members

  • Traceability tags attached to fittings and flanges

  • Material logs maintained by QA/QC department

4.1 Records

The following records should be maintained:


Traceability records are essential for future maintenance, audits, and regulatory compliance.

4.2 Project Documented Information

Project documentation should include:

  • Method Statement

  • Risk Assessment

  • Inspection & Test Plan

  • Welding Procedures (WPS/PQR)

  • NDT Reports

  • Hydrostatic Test Reports

  • Material Traceability Records

  • Final Acceptance Certificate

All documents should be compiled into a Project Quality Dossier for submission to the client. (included in the Project Quality Plan or Project Execution Plan (depending on role in the project whether a contractor/sub-contractor/consultant)