This is an independent, non-expert third-party perspective on the proposed redevelopment of Wisma Damansara. The views below are based on my personal understanding and publicly available information. They are not intended to influence ongoing residents’ protests, nor the developer’s obligations to comply with all relevant laws and regulations.


1) PROPOSAL

The old Wisma Damansara, a 16-storey commercial building, is proposed to be redeveloped into two 60-storey towers comprising residential and commercial/retail components.


The project carries a proposed plot ratio of ~1:9.6, which many residents argue is excessive compared to the 1:6 figure reflected in the KL Local Plan 2040 for the area.

The developer (BRDB) has submitted the proposal as a flagship project. DBKL held a Rule-3 consultation, receiving hundreds of objections primarily on density and traffic. Both DBKL and the developer have stated the application is under review based on the KL Local Plan and redevelopment incentive rules.

2) KEY CONCERNS BY RESIDENTS (Beyond Traffic Congestion)

2.1 Plot Ratio and Density

The proposed density far exceeds planning guidelines, leading to concerns about overdevelopment. Some residents question whether redevelopment incentives (which allow higher plot ratios) are being applied appropriately, and whether sufficient oversight and accountability exist.


3) ZONING, LAND USE AND NEIGHBOURHOOD CHARACTER

The project departs significantly from the KL Local Plan 2040, raising fears of a precedent for further over-dense developments,

Damansara Heights and Bukit Damansara are historically low-density bungalow areas. High-rise towers are viewed as inconsistent with this character,

Concerns include loss of privacy, where tall buildings may overlook existing gardens and homes.

4) INFRASTRUCTURE STRAIN 

Beyond traffic, residents cite stress on water supply, sewage systems, utilities, and local roads.

Many argue infrastructure upgrades must come before approving higher-density projects, not after.

5) HEIGHT, SKYLINE AND VISUAL IMPACTS

Introducing 60-storey towers in a low-rise setting will alter the skyline and neighbourhood views,

Beyond aesthetics, technical issues such as shadowing, wind effects, and blocked views may arise.

6) GEOLOGICAL AND CONSTRUCTION RISKS 

Bukit Damansara’s rocky terrain may require heavy excavation and rock blasting, potentially affecting land stability,

Risks include vibration, noise, and possible damage to nearby structures.

While no direct reports specific to Wisma Damansara have surfaced, this remains a valid concern.

7) FACTS CHECK (PUBLIC RECORD)

Publicly available information on the redevelopment is limited.

What is visible: the developer’s proposal (high plot ratio, mixed-use towers), DBKL’s Rule-3 public consultation, and significant resident objections.

8) LIMITATIONS OF MY OPINION

At the time of writing, no full technical documentation has been publicly disclosed. It might be available though. Not limited to the following and the breakdown of explanation, the documentations are :


These requirements need to be addressed clearly in a Construction Management Plan and Contractual Requirements.

 10) Closing Note

 For a project of this scale, transparent disclosure of technical studies is essential to ensure that redevelopment proceeds responsibly, in line with planning law, and with due regard for community well-being.